Organizing the Planning Team > Implementation Plan >
Fifteen Weeks before Delivery
The planning coordinator:
- Identifies the members of the planning team.
- Orders the printer.
- Orders the IBM Advanced Function Presentation licensed programs.
- Orders any additional hardware that is required, such as the
turnbar/flipper device for the 'h' printer configuration.
- Verifies the order for the appropriate channel cables, System/370, ESCON, TCP/IP,
and for any required channel extender, converter, or switching hardware boxes
in the channel interface.
- Prepares a plan for selecting and testing forms for use with the printer.
The physical planner:
- Determines the location for the printer and arranges for any changes to
the site. Ensures that the site will have conductive flooring.
- Identifies the delivery route for the printer.
- Prepares a space layout plan.
- Determines who will install the electrical wiring and outlets.
- Determines the type of electrical attachment and ground-fault circuit
protection to be used.
The system programmer:
- Determines the Advanced Function Presentation licensed programs needed.
- Creates a conversion plan for line-printer data and electronic overlays.
The application programmer:
- Identifies the applications that must be changed for migration to the
printer.
- Prepares a detailed plan for converting and testing applications that
will be used with the printer.